How to set up planning to run at the same time on a daily basis.


Symptom Want to run planning in the backround

Solution ID = KB-707

Goal : How to set up planning to run at the same time on a daily basis.

Version = Syteline7.XX.XX

Module : SLMFG

Fact 1 : Planning

Fact 2 : Background queue

Symptom 1 : How can I run the Planning activity in the Background?

Symptom 2 : Want to run APS nightly

Database : SQL

Cause

Steps to set up in the Background Queue
1.  Open Planning Form
2.  Select Action, then Background.  The Background Queue Form now appears.
3.  Select the Frequency and the Time of Day to run.  Caution -- select a time that won't conflict with other activities.
4.  Hit OK. Also see other related solutions:

2003syteline8671 -- how to set up scheduling in the background queue
2003syteline8672 -- how do I know if planning/scheduling are setup in the background queue?
2003syteline8673 -- how can I tell what time and frequency planning and scheduling are running in the background queue?